Managing complexity: the hospital construction site in operation

3 hours ago
4 min read
Fragment of a joist reinforcing bar, cut during core drilling in a hospital floor slab

Coordination, safety and operational continuity in the transformation of healthcare facilities


A building that never stops

In a hospital that remains in operation, the construction site does not occupy an empty space. It coexists with active wards, clinical routes, running building services and staff working a few metres away from the works. Many site decisions have an immediate effect on an activity that cannot be interrupted.

This is why, in my experience, hospital sites are among the most dynamic an architect can direct. Conditions change from day to day, sometimes from hour to hour. The design sets the objectives, but it cannot foresee everything that will happen between the handover of the works and final acceptance.


The problem starts before the site

The most recurrent difficulty arises before the works begin. In the older healthcare facilities I have worked on, a reliable survey of the existing condition is rarely available: the documentation, when it exists, often fails to describe floor slabs, building services and the transformations layered over decades.

This incomplete knowledge comes together with compressed design schedules and equally tight delivery times. The design is inevitably developed on a building that is only partly known. During the works, information emerges that no preliminary survey had revealed. It is up to the works supervision team to recognise it promptly, assess it and share it with designers, the contracting authority and the safety coordinator, so that it is handled through the proper procedures.

From this perspective, not every variation or unforeseen event points to a design error: many stem from initial knowledge that could not be complete. Precisely for this reason they must be recognised, distinguished and managed.


One hole, two floors

One episode makes the nature of the problem clear. During a refurbishment in a hospital, a few openings had to be cut through the floor slab for new drainage pipes running to the floor below.

The wet core drilling hit an undocumented joist reinforcing bar. Cutting the bar lengthened the operation and, with it, the amount of water used by the core drill. The water found its way into the hollow clay blocks of the slab and travelled through them to a point far from the hole.

Core-drilled hole in the floor slab, seen from the floor above

Above: the core-drilled hole in the floor slab.

It came out at the slab soffit through the hole of an old wall plug, once used to anchor the top of a shelving unit. Below, that shelving held medicines.

Water stains on the slab soffit, in the room below

Below: the stains on the soffit, in the room underneath.

The risk of process water reaching other rooms was known; the path it actually took was not predictable. The work was stopped and made safe, and the water was contained with very untheoretical means: buckets and cloths, together with the staff on site. The medicines, stored in cardboard boxes, were moved and their integrity was checked by the healthcare staff.

These are the events that make the need for a real presence of the works supervision team strikingly clear: not because it has to act in person, but because the process must be managed from every point of view.


Not everything can be prevented

The episode is an uncomfortable reminder: even after preventive measures, a residual risk remains in an existing building in operation. Preliminary investigations, scanning the reinforcement before cutting openings and protecting the rooms below reduce it, but do not eliminate it.

What counts, then, is how quickly the event is recognised and contained. Here an effective presence on site, proportionate to the critical works, becomes a control tool. The site supervisor present that day helped contain the event together with the contractor and the healthcare staff: a very concrete way of exercising one's role.


The languages of coordination

An event like this involves, within minutes, parties with different priorities. Hospital management must protect patients and activities. The contractor must ensure correct and safe execution, on time and on budget. The contracting authority must protect the contract and the public interest. The safety coordinator checks that measures remain adequate to the new conditions, and the project manager for the public client governs the decisions that affect the contract.

Holding these needs together often means explaining the same problem to people who speak different professional languages, and deciding under pressure without becoming rigid. In a hospital in operation, these skills are part of the coordination toolkit, alongside the programme and the site instruction.

One of the fascinating aspects of works supervision is that you find yourself in a situation that pushes you, almost physiologically, to engage in advanced, multi-level reasoning. The complexity comes, quite simply, from the number of parties you interact with and from the extreme dynamism of events, works, workforce and decisions.

In practice, it means translating the same information into the language of healthcare staff, of the contractor and of the contracting authority. And reading every operation also for what it produces outside its own boundaries: as on that day, on the floor below.


Turning the unexpected into knowledge

If the initial problem is incomplete knowledge of the building, the methodological answer is to build that knowledge during the works. Every discovery — a joist, an unrecorded service, a clash — must be recorded immediately, made available to the parties concerned according to roles and responsibilities, and archived with care.

In practice this means preliminary inspections before critical works, stable communication channels with hospital management and the contractor, work phases agreed with the wards, timely minutes and site instructions, and systematic photographic records. And digital environments where data is not lost: in my practice I use Trimble Connect for shared document management and Notion to organise operational knowledge.

This documentary discipline has three effects. It enables faster decisions, because information is where it is needed. It makes decisions verifiable and allows responsibilities to be traced. And, if it flows into the final as-built documents handed over to the facility, it leaves the hospital with a building that is better known than it was at the start.


The architect in the process

A hospital site in operation shows with particular clarity an issue that concerns every intervention on existing buildings: the quality of the work does not depend only on the design, but on the ability to govern its implementation.

In a necessarily multidisciplinary process, the contribution of the architect in works supervision lies in reading what happens beyond the boundaries of a single operation, as on that day on the floor below, and in making sure that what the site discovers becomes shared knowledge. It is work that is rarely visible, and that is precisely why it is worth telling.


SPa
 
 
 